thecodingcompany
Quantitative Aptitude

Time and Work

Rates of work, combined effort, pipes and cisterns and efficiency-based variation.

Questions5 solved
WeightHigh
GroupQuantitative Aptitude

What to know first

Cover these concepts before attempting the questions below. Skipping this step is why candidates plateau.

  • Work as a rate: one day’s work = 1/n of the job
  • Combined rates for two or more workers
  • Efficiency and men–days proportionality
  • Pipes and cisterns, including leak problems

5 questions with full solutions

The correct option is highlighted. Read the explanation even when you get it right — the method is the point.

01A can finish a job in 12 days and B in 18 days. Working together, how long will they take?
  1. A.6.8 days
  2. B.7.2 days
  3. C.7.5 days
  4. D.8 days
Solution. Combined rate = 1/12 + 1/18 = 3/36 + 2/36 = 5/36 of the job per day. Time = 36/5 = 7.2 days.
02If 6 men can complete a wall in 8 days, how long will 4 men take?
  1. A.10 days
  2. B.12 days
  3. C.14 days
  4. D.16 days
Solution. Total work in man-days = 6 × 8 = 48. With 4 men, time = 48/4 = 12 days. Work is conserved when you change the workforce.
03Two pipes fill a tank in 20 and 30 minutes. A third pipe empties it in 15 minutes. With all three open, how long to fill the tank?
  1. A.40 minutes
  2. B.60 minutes
  3. C.75 minutes
  4. D.120 minutes
Solution. Net rate = 1/20 + 1/30 − 1/15. Put over 60: 3/60 + 2/60 − 4/60 = 1/60 per minute. The tank fills in 60 minutes.
04A is twice as efficient as B and together they finish a job in 8 days. In how many days can A alone do it?
  1. A.10 days
  2. B.12 days
  3. C.14 days
  4. D.16 days
Solution. Let B’s rate be r, so A’s is 2r and combined is 3r = 1/8, giving r = 1/24. A alone works at 2r = 1/12, so A takes 12 days.
05A and B can do a job in 10 days, B and C in 15 days, A and C in 12 days. How long will all three take together?
  1. A.6 days
  2. B.8 days
  3. C.9 days
  4. D.10 days
Solution. Adding the three pair-rates gives 2(A+B+C) = 1/10 + 1/15 + 1/12 = 6/60 + 4/60 + 5/60 = 15/60 = 1/4. So A+B+C = 1/8, and together they take 8 days.
Solution answers are worked values. Where a decimal result is not one of the options, the closest listed option is marked correct; the explanation gives the exact figure.

Practise here. Get placed there.

Prep+ is unlimited practice. When you are ready to turn it into an offer, TCC Placement Partner handles portfolio, resume and interviews.